Cape Jaffa Marina Dredging Restoring Safe Access After Storms

Dredging operations at Cape Jaffa Marina are in full swing, with crews making significant progress to restore the marina’s functionality after recent storm damage.

Daily Progress: Moving 1,500 Cubic Meters of Sand

The dredging team is relocating approximately 1,500 cubic meters of sand each day to the eastern side of the marina. This effort is part of a broader initiative to clear the channel and ensure safe navigation for vessels.

Expediting Reopening with Targeted Dredging

According to the Kingston District Council (SA), the current focus is on dredging a channel between the two groynes. This strategic approach is designed to speed up the reopening process and minimize disruptions for marina users.

Project Timeline: November to December 2024

The dredging project began in late November 2024 and is expected to continue through December. Despite earlier efforts this year, additional work became necessary due to the extensive impact of recent storms.

Storms Undermine Early 2024 Efforts

In early 2024, approximately 75,000 cubic meters of sand was dredged and relocated. However, severe weather conditions caused significant sediment accumulation, negating much of the progress made earlier in the year.

Revised Goals: Addressing New Challenges

A recent survey revealed that roughly 100,000 cubic meters of sand must now be dredged and relocated to restore the marina to its pre-storm condition. This revised goal underscores the scale of the challenge and the resilience of the dredging team.

Sustaining Safe Navigation for the Future

The Cape Jaffa Marina dredging project highlights the importance of ongoing maintenance in the face of natural challenges. By tackling these obstacles head-on, the marina aims to ensure a safe and functional environment for boaters and the surrounding community.