Dredging Challenges Persist as Chittagong Port Works on Matarbari Deep Seaport Channel

The Matarbari deep seaport, a significant infrastructure project in Bangladesh, is designed to boost the country’s maritime capacity and economic growth. Opened in April 2023, this deep seaport allows larger vessels to dock, especially coal-carrying ships. However, the channel connecting the Bay of Bengal to the seaport has faced ongoing dredging challenges due to sediment accumulation. In response, Chittagong Port Authority (CPA) has initiated dredging operations, marking a crucial milestone as the port undertakes this task without foreign assistance for the first time. This decision is expected to save the port an impressive Tk 3.5 billion annually, yet several dredging challenges remain in the process.

1. The Importance of Matarbari Deep Seaport Channel

Strategic Location and Purpose

Matarbari, located in the Maheshkhali area of Cox’s Bazar, is a vital link in Bangladesh’s economic and shipping infrastructure. The seaport is part of a broader initiative to expand the nation’s coal import capabilities, supporting the country’s growing power generation needs. The deep seaport’s construction allows large coal-carrying vessels, which were previously unable to dock at Chittagong Port, to now arrive directly at Matarbari. This channel is a crucial part of Bangladesh’s plan to enhance its global trade position and maritime capacity.

The Channel’s Construction History

The channel, stretching 14.3 kilometers and designed to be 16 meters deep, was constructed by the Power Generation Company Bangladesh with funding from JICA (Japan International Cooperation Agency). Initially completed in 2023, it was transferred to Chittagong Port Authority in September of that year. However, despite its relatively recent construction, the channel began to experience problems with sediment accumulation, significantly reducing its depth in some areas. These dredging challenges began to surface almost immediately, slowing the efficiency of the channel.

2. The Dredging Process

The Need for Dredging

As silt accumulated in the Matarbari channel, the depth in some parts decreased from the planned 16 meters to just 10 meters. This posed a significant problem, as the shallower depth impacted the navigability of large ships that rely on deeper channels for safe docking. To address this issue, Chittagong Port began dredging efforts to remove the accumulated sediment and restore the channel’s capacity. Dredging challenges are an inherent part of this process, but they are necessary for maintaining the safe and efficient movement of vessels, ensuring that Matarbari can operate at full capacity.

Chittagong Port’s Self-Reliance in Dredging

For the first time, Chittagong Port has taken on the responsibility of dredging the Matarbari channel without foreign assistance. This is a significant development, as the port has typically relied on foreign contractors for such tasks. By managing the dredging internally, the port expects to save at least Tk 3.5 billion each year, a cost that would have otherwise gone to foreign companies. The use of domestic resources in dredging also signifies the growing self-sufficiency of Bangladesh’s maritime operations. Overcoming dredging challenges locally has helped strengthen Bangladesh’s capabilities in handling its maritime infrastructure.

3. Challenges Faced During Dredging

Sediment Accumulation and Channel Instability

The accumulation of sediment in the Matarbari channel has posed multiple dredging challenges. As the newly constructed channel is still settling, the breakwater and surrounding areas are not fully stable. The shifting and instability of the seabed make dredging operations more difficult. Moreover, the ongoing sediment build-up adds complexity to the task, making it harder for the dredger to maintain optimal depths consistently. The continued dredging challenges presented by sediment accumulation are something Chittagong Port must carefully manage to prevent further disruptions.

Difficult Soil Conditions

In addition to the challenges of sediment accumulation, the clay soil in the Matarbari channel has proven to be much harder to dredge compared to the sandy soil of the nearby Karnaphuli channel. The port’s dredging team has had to adapt to these challenging soil conditions, but they remain optimistic that they can overcome these hurdles in the coming months. The experience gained from dredging the Karnaphuli channel has been helpful, although Matarbari’s unique conditions require specialized attention. These dredging challenges have made the operation more complex but also more rewarding as the port looks to achieve long-term results.

4. Key Players Involved in the Dredging Operation

Chittagong Port Authority’s Efforts

Under the leadership of Chittagong Port’s senior officials, including Senior Dredging Master Lt Commander Md Ashiqe Mahmud and Chief Hydrographer Commander Mohammad Shamsit Tabriz, the dredging operation is progressing despite the obstacles. Their expertise is essential to ensure that the dredging continues smoothly and that the channel reaches the required depth for safe navigation. Chittagong Port is committed to overcoming the dredging challenges posed by the difficult environment in Matarbari.

The Dredging Equipment and Techniques

The port’s dredging efforts rely on specialized equipment designed for these tough conditions. The dredger being used has a higher capacity than those employed in previous dredging projects, allowing it to handle the unique challenges presented by Matarbari’s sediment and soil conditions. This equipment is critical to achieving the depth required for large vessels to safely enter the port. Overcoming these dredging challenges requires high-tech solutions that are capable of dealing with both sediment build-up and tough soil conditions.

5. Looking Ahead: The Future of Matarbari Deep Seaport

Anticipated Outcomes of the Dredging Project

Once the dredging process is complete, the Matarbari deep seaport channel will be restored to its full depth, allowing larger vessels to dock more efficiently. This will improve Bangladesh’s shipping capabilities, reduce reliance on foreign ports, and contribute to the nation’s overall economic growth. The dredging will also facilitate smoother coal importation, which is vital for the country’s energy generation needs. Despite the dredging challenges, the outcome of this project will significantly impact the region’s trade and energy sectors.

Overcoming Future Challenges

Chittagong Port is committed to implementing solutions to prevent future sediment build-up. Ongoing monitoring and periodic dredging will be necessary to ensure the channel remains navigable. The port authorities are confident that, with the right strategies and continued improvements in dredging techniques, these dredging challenges will be overcome. Long-term solutions will help ensure the stability of the channel and the continued growth of the Matarbari seaport.

Conclusion

Chittagong Port’s efforts to dredge the Matarbari deep seaport channel represent a significant milestone in Bangladesh’s maritime infrastructure development. While challenges such as sediment accumulation and difficult soil conditions persist, the port’s self-reliant approach promises long-term cost savings and greater operational efficiency. As dredging continues, the Matarbari channel will be restored to its intended depth, further solidifying Bangladesh’s position as a growing hub for global trade and energy generation. Despite the ongoing dredging challenges, the future looks bright for Matarbari’s success in the global maritime arena.