The Houston Ship Channel Expansion, known as Project 11, continues to make significant strides. During the Port of Houston Commission’s meeting on Tuesday, September 24, Chairman Ric Campo provided an update, highlighting the progress and upcoming milestones in this critical infrastructure project.

Key Updates from the Port of Houston Commission Meeting

On September 24, the Port of Houston Commission gathered for its regular monthly meeting, with Chairman Ric Campo delivering key insights into the advancement of Project 11. The expansion project, aimed at enhancing the capacity of the Houston Ship Channel, is progressing as planned, with major segments set for completion by November.

Major Milestones in the Houston Ship Channel Expansion

Galveston Bay Channel Expansion

One of the primary focus areas is the expansion through Galveston Bay, which will enable larger vessels to access the Bayport Container Terminal. This development will enhance the efficiency of the port and accommodate larger shipping demands.

Environmental Sustainability: A Top Priority

Chairman Campo emphasized the project’s strong commitment to environmental sustainability. Multiple dredges involved in the expansion are outfitted with advanced technology that meets the Environmental Protection Agency’s (EPA) stringent Tier 4 air emission standards. This step ensures that the expansion is environmentally responsible and minimizes its impact on the surrounding ecosystem.

Progress on Project 11 Contracts

During the meeting, a staff report revealed that five of the 14 planned contracts for Project 11, managed jointly by Port Houston and the U.S. Army Corps of Engineers (USACE), have been successfully completed.

Segment 1A: Bolivar Roads to Redfish

A notable achievement was the completion of the Segment 1A (Bolivar Roads to Redfish) contract. This segment was finished ahead of schedule and under budget, saving $5.8 million. This accomplishment highlights the efficiency of the ongoing efforts to expand the Houston Ship Channel.

Aids to Navigation Relocation in Segment 2

The Aids to Navigation (ATON) relocation in Segment 2 (Bayport) is another key component of the project. This relocation is scheduled to be completed by mid-October, further enhancing the overall functionality of the expanded channel.

Ongoing Work and Future Plans

Dredging Operations in Segment 1C

Dredging operations for Segment 1C, which spans from Bayport to Barbours Cut, began in August. The contractor, Callan Marine, is using the General Arnold, a 32-inch cutter suction dredge equipped with Tier 4 engines, to execute this part of the project. The environmentally friendly dredge is expected to complete this segment by the second quarter of 2025.

Segment 3 Construction Set to Begin

In addition to the ongoing work, the USACE recently awarded the contract for Segment 3 (Barbours Cut) at the end of July. Construction is expected to commence soon, continuing the expansion efforts that will ultimately increase the capacity and efficiency of the Houston Ship Channel.

Environmental and Economic Benefits of Project 11

The Houston Ship Channel Expansion – Project 11 – is not just a massive infrastructure project but also a key driver for economic growth and environmental sustainability. By enabling larger vessels to access the port, improving navigability, and adhering to strict environmental regulations, this expansion will solidify the Port of Houston’s role as a critical hub for global trade.

Conclusion

The Houston Ship Channel Expansion is on track to meet its critical milestones, with several key segments nearing completion. The project’s commitment to sustainability, coupled with its efficient execution, ensures that the Port of Houston will continue to thrive as a vital gateway for international shipping and commerce.