Pinellas County, Florida, is gearing up for an extensive beach renourishment initiative at Pass-a-Grille Beach. This revitalization effort will unfold in two strategic phases, aimed at enhancing both safety and sustainability.
Phase One: Sand Allocation
In the initial phase, an estimated 10,000 to 15,000 cubic yards of sand will be utilized, sourced from the Grand Canal dredging project. This replenishment will target the shoreline spanning from 1st Avenue to 9th Avenue.
Phase Two: Expansion and Enhancement
Moving forward, Pinellas County is actively pursuing a permit from the U.S. Army Corps of Engineers for phase two. This phase will see the infusion of an additional 138,000 cubic yards of sand from Pass-a-Grille Inlet, extending the renovation efforts from 22nd Avenue to 1st Avenue.
Operational Details and Schedule
Phase one operations are scheduled to run from 7 a.m. to 7 p.m., seven days a week. Pending approval of phase two, operations will intensify, transitioning to round-the-clock efforts to expedite the renovation process.
Project Objectives
The primary goals of this project are twofold: to bolster boater safety and to enhance the longevity and resilience of Pass-a-Grille Beach. These efforts align with the broader mission of sustainable coastal management and conservation.
Temporary Closure of Southwest Beach Fishing Pier
As part of the renovation adjustments, the fishing pier at Southwest Beach will undergo temporary closure, commencing in early June. This measure ensures the safety of visitors and facilitates uninterrupted renovation activities.
Conclusion The Pass-a-Grille Beach renourishment project represents a proactive step towards safeguarding and enhancing one of Pinellas County’s most cherished coastal assets. By prioritizing safety, sustainability, and community well-being, this initiative sets a precedent for responsible coastal management practices.