U.S. Army Corps of Engineers, Jacksonville District, began maintenance dredging of the federal navigation channel (also known as Matanzas Pass) near Fort Myers Beach, Florida.
Contract Award to Cottrell Contracting Corp.
The project is being executed under a $2.9 million contract awarded in June to Cottrell Contracting Corp. of Chesapeake, Virginia. It is expected to be completed in late August or early September. The project calls for the dredging of approximately 120,000 cubic yards of shoaling from Cuts 1, 2A, and 3 of the federal channel, including wideners and settling basin, to a required depth of 12 feet plus 2 feet of allowable over-depth.
Dispersal of Dredged Material
All dredged material will be dispersed in a nearshore placement area approximately 8,000 feet south of the dredged channel, progressing north to south for about one mile. The dredge pipe will be weighted and submerged, and its underwater route will be marked with orange poly balls and lighted danger diamond buoys. Dredging and placement will continue 24 hours a day, seven days a week, until the project is complete.
A local Notice to Mariners has been issued, and USACE requests all boaters and navigators to respect the slow speed and minimum wake signs when passing the dredge. USACE also requests boaters avoid anchoring and swimming in clearly delineated sections along the shoreline as the placement area progresses southward along Fort Myers Beach. Beachgoers should avoid wading on the beach shoreline adjacent to the discharge areas.
The USACE team and Lee County will conduct protective sea turtle nest and shorebird monitoring throughout the project. Lee County may relocate turtle nests in the vicinity of the project staging area at Bowditch Point Park and requests the public respect markers and barriers that may be erected along the beach to mark nests being protected on site.