Doggerland and Abeko

In the latter part of the previous year, the company secured a public tender to serve as the principal contractor for deepening the channel leading to the Grimsby GRT terminal.

This channel plays a vital role in accommodating the docking and unloading of larger car carriers, especially during low tides. Therefore, the dredging of the channel was deemed necessary to enhance the operational efficiency of the Grimsby port.

Reviving Underwater Landscapes: A Look into the Completion of the Doggerland and Abeko Dredging Venture

Throughout the project, Doggerland operated around the clock, employing the backhoes Abeko Server 1 and Abeko Server 2, both equipped with a Hitatchi 1200 triple and a 5.5 m3 water volume bucket.

Dredging Success: Doggerland and Abeko Wrap Up Large-Scale Project in the UK

During the dredging operations, the crews managed to excavate over 500,000 cubic meters of clay, transporting it to the designated dumpsite HU-080, which required approximately a 45-minute round trip by sea.

Additionally, for a brief period, Abeko Server-3, outfitted with a Komatsu PC-800, also participated in the dredging activities within the channel.

Leave a Reply

Your email address will not be published. Required fields are marked *